List of projects done by pyramid Control Systems Pvt. Ltd. for Vedanta group

LIST OF JOBS DONE FOR VEDANTA GROUP BY PYRAMID CONTROL SYSTEMS PVT LTD.


S.NO. CUSTOMER CONTRACTOR JOB DONE  BY PRAMID STATUS
1. Sterlite Industries
Sylvasa.
Encon Furnaces (P) Ltd. Complete electrical, instrumentation, Digital DC drives  Commissioned in Aug. - 2002.
2 Sterlite Industries
Sylvasa.
Encon Furnaces (P) Ltd. Complete electrical, instrumentation, DC drives etc. for wire rod plant comprising aluminium melting & holding furnaces & rod mill plus PLC, HMI & Servo drives Commissioned in 2004
3 Sterlite Industries
Sylvasa.
Encon Furnaces (P) Ltd. Revamping of job at S.No. 1 plus PLC, HMI & Servo drives Commissioned in 2006
4 Sterlite Optical Technologies Hardware Encon Furnaces (P) Ltd. Instrumentation work (Part) Commissioned in 2007
5 Sterlite Industries Pune Direct Retrofit of 60KW thyristor power pack in an electrically heated furnace. Commissioned in 2006
6 BALCO, Korba Escorts Ltd. Faridabad 200KW Thyristor controlled Heater Control panel with PLC, HMI & Instruments Commissioned in 2006
7 BALCO, Korba Sandvik Asia Ltd., Hosur, TN. 70KW Heater control panel Commissioned in 2007
8 Vedanta Aluminium Jharsuguda Sandvik Asia Ltd., Hosur, TN. 2x220KW Thyristor controlled heater control panels with PLC, HMI & instruments for GAP-1 & 2 GAP- 2 Commissioned in July 2008
9 Sterlite Technologies
Haridwar
Encon Furnaces (P) Ltd. Faridabad Complete electrical, instrumentation, DC drives etc. for wire rod plant comprising aluminium melting & holding furnaces & rod mill plus PLC, HMI Commissioned in March 2009
10 Sterlite Technologies Haridwar Direct VFD panels from 30 HP to 120 HP with Honeywell Magnetic Water Flow transmitters, Wika pressure transmitter and PID controllers for Air Blower, Water Pumps and Screw Compressor applications for energy savings Commissioned in April 2009